675 Ind. Admin. Code 30-3-10

Current through January 8, 2025
Section 675 IAC 30-3-10 - Preparation for inspection; notice

Authority: IC 22-13-2-8

Affected: IC 22-15-6

Sec. 10.

The owner or user shall prepare each boiler or unfired pressure vessel for internal inspection and shall prepare for and apply a hydrostatic leak test whenever necessary, on the date specified by the inspector responsible for inspection of the equipment in question, which date shall be no less than fourteen (14) days after the date of notification.

675 IAC 30-3-10

Fire Prevention and Building Safety Commission; 675 IAC 30-3-10; filed Jan 5, 1996, 10:15 a.m.: 19 IR 1115; readopted filed Jul 9, 2001, 1:33 p.m.: 24 IR 3822; readopted filed Sep 21, 2007, 9:16 a.m.: 20071010-IR-680070389RFA; readopted filed Oct 19, 2007, 1:08 p.m.: 20071114-IR-680070389RFA; readopted filed Sep 5, 2013, 10:09 a.m.: 20131009-IR-680130182RFA; readopted filed 9/4/2019, 2:20 p.m.: 20191002-IR-675190336RFA
Filed 4/28/2021, 11:03 a.m.: 20210526-IR-675200627FRA, eff 7/1/2021

Transferred from the Boiler and Pressure Vessel Rules Board ( 680 IAC 2-3-10) to the Fire Prevention and Building Safety Commission ( 675 IAC 30-3-10) by P.L. 249-2019, SECTION 15, effective July 1, 2019.