675 Ind. Admin. Code 14-4.4-174

Current through May 29, 2024
Section 675 IAC 14-4.4-174 - Section P3005.2.4; changes of direction

Authority: IC 22-13-2-2; IC 22-13-2-2.5; IC 22-13-2-13

Affected: IC 22-12; IC 22-13; IC 22-14; IC 22-15; IC 36-7

Sec. 174.

Change the text of SECTION P3005.2.4 to read as follows:

Where a horizontal drainage pipe or a building drain has a change of horizontal direction greater than 45 degrees (0.79 rad), a cleanout shall be installed at the change of direction. Where more than one change of horizontal direction greater than 45 degrees (0.79 rad) occurs within 40 feet (12,192 mm) of developed length of piping, the cleanout installed for the first change of direction shall serve as the cleanout for all changes in direction within that 40 feet (12,192 mm) of developed length of piping.

675 IAC 14-4.4-174

Fire Prevention and Building Safety Commission; 675 IAC 14-4.4-174; filed 11/26/2019, 11:43 a.m.: 20191225-IR-675190330FRA