Current through December 12, 2024
Section 329 IAC 10-32-2 - Plot plans and cross-sectional drawingsAuthority: IC 13-14-8-7; IC 13-15-2-1; IC 13-19-3-1
Affected: IC 13-30-2; IC 36-9-30
Sec. 2.
(a) An application for a restricted waste site Type III or a construction/demolition site must be accompanied by plot plans using a scale of at least one (1) inch equals one hundred (100) feet for a site of less than eighty (80) acres, or a scale of at least one (1) inch equals two hundred (200) feet for a facility of eighty (80) acres or more. A bar scale must be shown on plans in order to properly indicate the scale if size changes occur. All plot plans must include the facility boundaries and indicate each of the required features set forth in this section within three hundred (300) feet of the facility boundaries. All facility plan elevations must correlate with United States Geological Survey (USGS) mean sea level data.(b) An application for restricted waste site Type III must be accompanied by the following plot plans and cross sections:(1) A plot plan that indicates the following:(A) Locations and elevations of all existing and proposed on-site boring locations.(C) Surface water run-off direction.(E) Utility easements and rights-of-way.(F) Present land surface contours at intervals of no more than five (5) feet.(G) Proposed location of scales required by 329 IAC 10-14-2.(2) A plot plan that indicates the fill boundaries and proposed final contours of the site at intervals of no more than two (2) feet.(c) An application for a construction/demolition site must be accompanied by the following plot plans and cross sections:(1) A plot plan that indicates the following:(A) Locations and elevations of all existing and proposed on-site boring locations.(C) Surface water run-off direction.(E) Utility easements and rights-of-way.(F) Present land surface contours at intervals of no more than five (5) feet.(G) Proposed location of scales required by 329 IAC 10-14-2.(2) A plot plan that indicates the fill boundaries and proposed final contours of the site at intervals of no more than two (2) feet.(3) A plot plan, with surface contours at intervals of no more than five (5) feet, which indicates initial facility development. Compliance with this plan is a preoperational requirement under 329 IAC 10-35-2. Benchmarks as required by 329 IAC 10-35-2 must be shown with a description and elevation provided.(4) A plot plan, with surface contours at intervals of no more than five (5) feet, which indicates the following: (A) Land surface water diversion structures.(C) Vegetation or fences for visual screening.(D) Sedimentation control structures and erosion control structures.(F) Leachate collection and methane control systems if proposed.(G) Existing and proposed structures.(H) The precise location of the solid waste boundary.(I) Methods of operation.(J) Direction and the order operation and development will proceed.(L) Length and width of trenches if proposed.(M) Depth of lifts and size of working face.(N) Areas of the site to be used only for acquisition of cover soil.Solid Waste Management Board; 329 IAC 10-32-2; filed Mar 14, 1996, 5:00 p.m.: 19 IR 1909; readopted filed Jan 10, 2001, 3:25 p.m.: 24 IR 1535; readopted filed May 14, 2007, 1:53 p.m.: 20070523-IR-329070138BFAReadopted filed Jul 29, 2013, 9:20 a.m.: 20130828-IR-329130179BFA; readopted filed Jun 14, 2019, 2:00 p.m.: 20190710-IR-329190249BFA