Sec. 8.5.
The following compliance schedule must be followed:
Permit Compliance Schedule | |
To apply for coverage | Submit a completed NOI letter |
1st year of permit coverage | Submit results of sampling data |
Develop and implement the SWP3 | |
Submit SWP3 certification checklist | |
Submit annual report | |
2nd year of permit coverage | Submit results of sampling data |
Submit annual report | |
3rd year of permit coverage | Submit results of sampling data |
Submit annual report | |
4th year of permit coverage | Submit results of sampling data |
Submit annual report | |
5th year of permit coverage | Submit results of sampling data |
Submit annual report | |
90 days before permit expires | Resubmit a completed NOI letter |
Permit renewals | Repeat annual sampling schedule |
Submit SWP3 certification checklist during the first year of renewal coverage only if substantial changes have been made on site or to the plan since its inception Submit annual reports |
The compliance schedule begins from the date on the initial NOI letter submittal or the expiration date of the previous five (5) year permit term. All submittals to the commissioner must be sent to:
Indiana Department of Environmental Management
Office of Water Quality
100 North Senate Avenue, Room N1255
Indianapolis, Indiana 46204.
327 IAC 15-6-8.5