A continuous compliance plan for a source to which 326 IAC 6.8-7 applies shall contain a schedule for complying with the requirements of 326 IAC 6.8-7. The schedule shall list specific compliance dates for the following actions:

(1) Submittal of plans.
(2) Start of construction.
(3) Completion of construction.
(4) Achieving compliance.
(5) Performing compliance tests.
(6) Submitting compliance test results.