Ill. Admin. Code tit. 92 § 800.440

Current through Register Vol. 49, No. 1, January 3, 2025
Section 800.440 - Force Majeure

In the event that the recipient or a contractor is delayed, hindered in, or prevented from the performance of any act required by the contract by reason of any of the following:

a) strikes, lockouts, labor troubles;
b) unduly harsh weather conditions, not including foreseeable and ordinary adverse weather conditions such as rain and snow, which prevent the normal performance of the rehabilitation project;
c) inability to procure materials;
d) failure of power;
e) riots, insurrection, or war; or,
f) any Act of God;

the time of performance of such delayed party may be extended for a time period equal to such delay.

Ill. Admin. Code tit. 92, § 800.440