The following requirements apply to all electrical generators used to provide electrical power to any nonmetallic mineral processing plant. The requirements apply to each site of operations. (3-28-23)
Rated Output Capacities (kW) | Allowable Operating Hours (hr/day) | Allowable Operating Hours (hr/yr) | ||
Attainment Unclassifiable Areas | PM-10 Nonattainment Areas | Attainment Unclassifiable Areas | PM-10 Nonattainment Areas | |
0 - 454 | 24 | 8 | 8760 | 2880 |
455 - 1000 | 24 | 24 | 8760 | 8760 |
1001 - 2000 | 24 | 24 | 5200 | 5200 |
kW = kilowatts | ||||
hr/day = hours per day | ||||
hr/yr = hours per year |
(3-28-23)
Idaho Admin. Code r. 58.01.01.798