Haw. Code R. § 3-125-18

Current through April, 2024
Section 3-125-18 - Default, delay, and time extensions for construction contracts

The following paragraphs, or similar statements expressing the intent of these paragraphs, shall be included in all construction contracts:

(1) "Default. If the contractor refuses or fails to perform the work, or any separable part thereof, with such diligence as will assure its completion within the time specified in this contract, or any extension thereof, fails to complete the worK within such time, or commits any other substantial breach of this contract, and further fails within seven days after receipt of written notice from the procurement officer to commence and continue correction of the refusal or failure with diligence and promptness, the procurement officer may, by written notice to the contractor, declare the contractor in breach and terminate the contractor's right to proceed with the work or the part of the work as to which there has been delay or other breach of contract. In that event, the State may take over the work and perform the same to completion, by contract or otherwise, and may take possession of, and utilize in completing the work, the materials, appliances, and plant as may be on the site of the work and necessary therefor. Whether or not the contractor's right to proceed with the work is terminated, the contractor and the contractor's sureties shall be liable for any damage to the State resulting from the contractor's refusal or failure to complete the work within the specified time."
(2) "Liquidated damages upon termination. If fixed and agreed liquidated damages are provided in the contract, and if the State so terminates the contractor's right to proceed, the resulting damage will consist of the liquidated damages for the time as may be required for final completion of the work."
(3) "Liquidated damages in absence of termination. If fixed and agreed liquidated damages are provided in the contract, and if the State does not terminate the contractor's right to proceed, the resulting damage will consist of liquidated damages until the work is completed or accepted."
(4) "Time extension. The contractor's right to proceed shall not be so terminated nor shall the contractor be charged with resulting damage if:
(A) The delay in the completion of the work arises from causes such as: acts of God; acts of the public enemy; acts of the State and any other governmental entity in either a sovereign or contractual capacity; acts of another contractor in the performance of a contract with the State; fires; floods; epidemics; quarantine restrictions; strikes or other labor disputes; freight embargoes; unusually severe weather; delays of subcontractors due to causes similar to those set forth above; or shortage of materials; provided, however, that no extension of time will be granted for a delay caused by a shortage of materials, unless the contractor furnishes to the procurement officer proof that the contractor has diligently made every effort to obtain the materials from all known sources, and further proof that the inability to obtain the materials when originally planned did in fact cause a delay in final completion of the entire work which could not be compensated for by revising the sequence of the contractor's operations; and
(B) The contractor, within ten days from the beginning of the delay (unless the procurement officer grants a further period of time before the date of final payment under the contract), notifies the procurement officer in writing of the causes of delay. The procurement officer shall ascertain the facts and the extent of the delay and extend the time for completing the work when, in the judgment of the procurement officer, the findings of fact justify such an extension."
(5)"Additional rights and remedies. The rights and remedies of the State provided in this contract are in addition to any other rights and remedies provided by law."

Haw. Code R. § 3-125-18

[Eff 12/15/95; am and comp NOV 17 1997] (Auth: HRS §§ 103D-202, 103D-501) (Imp: HRS § 103D-501)