Section 3-125-17 - Termination for default in goods and services contracts

The following paragraphs, or similar statements expressing the intent of these paragraphs, shall be included in all goods and services contracts:

(1) "Default. If the contractor refuses or fails to perform any of the provisions of this contract with such diligence as will ensure its completion within the time specified in this contract, or any extension thereof, otherwise fails to timely satisfy the contract provisions, or commits any other substantial breach of this contract, the procurement officer may notify the contractor in writing of the delay or non-performance, and if not cured in ten days or any longer time specified in writing by the procurement officer, the officer may terminate the contractor's right to proceed with the contract or a part of the contract as to which there has been delay or other breach of contract. In the event of termination in whole or in part, the procurement officer may procure similar goods or services in a manner and upon terms deemed appropriate by the procurement officer. The contractor shall continue performance of the contract to the extent it is not terminated and shall be liable for excess costs incurred in procuring similar goods or services."
(2) "Contractor's duties. Notwithstanding termination of the contract and subject to any directions from the procurement officer, the contractor shall take timely and necessary action to protect and preserve property in the possession of the contractor in which the state or county has an interest."
(3) "Compensation. Payment for completed goods delivered and accepted by the State shall be at the contract price. Payment for the protection and preservation of property shall be in an amount agreed upon by the contractor and procurement officer; if the parties fail to agree, the procurement officer shall set an amount subject to the contractor's rights under chapter 3-126. The State may withhold from amounts due the contractor as the procurement officer deems to be necessary to protect the State against loss because of outstanding liens or claims of former lien holders and to reimburse the State for the excess costs incurred in procuring similar goods and services."
(4) "Excuse for nonperformance or delayed performance. Except with respect to defaults of subcontractors, the contractor shall not be in default by reason of any failure in performance of this contract in accordance with its terms, if the contractor has notified the procurement officer within fifteen days after the cause of the delay and the failure arises out of causes including but not limited to the following: acts of God; acts of the public enemy; acts of the State and any other governmental body in its sovereign or contractual capacity; fires; floods; epidemics; quarantine restrictions; strikes or other labor disputes; freight embargoes; or unusually severe weather. If the failure to perform is caused by the failure of a subcontractor to perform or to make progress, and if the failure arises out of causes similar to those set forth above, the contractor shall not be deemed to be in default, unless the goods or services to be furnished by the subcontractor were obtainable from other sources in sufficient time to permit the contractor to meet the contract requirements. Upon request of the contractor, the procurement officer shall ascertain the facts and extent of the failure, and, if the officer determines that any failure to perform was occasioned by any one or more of the excusable causes, and that, but for the excusable cause, the contractor's progress and performance would have met the terms of the contract, the delivery schedule shall be revised accordingly, subject to the rights of the State under the clause entitled in fixed-price contracts, 'Termination for Convenience' and in cost-reimbursement contracts, 'Termination'. As used in this paragraph, the term 'subcontractor' means subcontractor at any tier."
(5) "Additional rights and remedies. The rights and remedies provided in this contract are in addition to any other rights and remedies provided by law."