Ga. Comp. R. & Regs. 110-2-8-.16

Current through Rules and Regulations filed through December 24, 2024
Rule 110-2-8-.16 - Required Changes to Existing Building System Approvals

When amendment of these rules requires changes to an approved building system documentation, the Commissioner shall notify the manufacturer of such rule changes, and shall allow the manufacturer ninety (90) days from the date of such notification, or such additional time as the Commissioner shall deem reasonable, in which to submit revised documents for approval. Revised documents submitted pursuant to this section shall be processed as supplemental.

Ga. Comp. R. & Regs. R. 110-2-8-.16

O.C.G.A. Sec. 8-2-113.

Original Rule entitled "Required Changes to Existing Building System Approvals" adopted. F. Sept. 25, 2000; eff. Oct. 15, 2000.
Repealed: New Rule of same title adopted. F. Mar. 4, 2003; eff. Apr. 1, 2003, as specified by the Agency.