The manufacturer shall compile a document labeled "Installation Procedures" which shall contain the necessary instructions needed to prepare the building for occupancy. The Installation Procedures shall list those items to be inspected or installed at the installation site and show in detail methods of placing each unit on site without functional damage. These designs shall include but not be limited to lift point designation(s), jacking points and stresses. Installation of industrialized buildings shall comply with the codes specified herein. A minimum of two (2) sets of Installation Procedures shall accompany each building or component when it leaves the manufacturing or re-manufacturing facility.
Ga. Comp. R. & Regs. R. 110-2-8-.14
O.C.G.A. Sec. 8-2-113.