Rule 27-1916 - PAYMENTS FOR SALVAGE AND REMOVAL
1916.1

A contract may provide that the District pay the contractor for the dismantling or demolition of a structure or that the contractor pay the District for the right to salvage and remove the materials resulting from the dismantling or demolition operation.

1916.2

The contracting officer shall determine whether the District shall retain materials resulting from a dismantling or demolition operation in accordance with §§ 1915.3 and 1915.4.

1916.3

If property is determined more useful to the District than its value as salvage to the contractor, the contract shall expressly designate that the property be retained by the District.

1916.4

The contracting officer, on advice of technical personnel, shall determine the fair market value of any property designated as salvage which will be retained by the contractor. The fair market value estimate shall be used in determining the amount of payment, if any, that will be made to the contractor.