Rule 27-1915 - DISMANTLING, DEMOLITION, OR REMOVAL OF STRUCTURES
1915.1

Contracts for dismantling, demolition, or removal of structures shall be awarded in accordance with either the Service Contract Act 1965 ( 41 U.S.C. §§ 6702 to 6707 ), or the Davis-Bacon Act ( 40 U.S.C. §§ 3141 to 3148 ), as follows:

(a) When the contract is solely for dismantling, demolition, or removal of a structure, the provisions of the Service Contract Act shall apply.
(b) When the contract is for dismantling, demolition, or removal of a structure, and further work will result in the construction, alteration, or repair of a public building or public work at the same location, even if by separate contract, the provisions of the Davis-Bacon Act shall apply with respect to the contract for dismantling, demolition, or removal of the structure and the contract for the construction, alteration, or repair of the public building or public work.
1915.2

When a contract is solely for dismantling, demolition, or removal of a structure, the contracting officer may require the contractor to furnish a performance bond or other security in accordance with the provisions of Chapter 27 of this title in an amount that the contracting officer considers adequate to do the following:

(a) Ensure completion of the work;
(b) Protect property to be retained by the District;
(c) Protect property to be provided as compensation to the contractor; and
(d) Protect the District against damage to adjoining property.