Strike Section A105.1 in Appendix A of the International Green Construction Code in its entirety and insert new Section A105.1 in Appendix A of the Green Construction Code in its place to read as follows:
Waste management project elective. Projects seeking a waste management project elective shall comply with Section 503.1, except that the nonhazardous construction waste materials required to be diverted from landfills shall be increased by 20 percent.
Strike Section A105.3 in Appendix A of the International Green Construction Code in its entirety and insert new Section A105.3 in Appendix A of the Green Construction Code in its place to read as follows:
Material selection project electives. Each of the following shall be considered a separate material selection project elective. The project electives are cumulative and compliance with each item shall be recognized individually.
Strike Table A105 in Appendix A of the International Green Construction Code in its entirety and insert new TableA105 in Appendix A of the Green Construction Code in its place to read as follows:
TABLE A105
MATERIAL RESOURCE CONSERVATION AND EFFICIENCY
PROJECT ELECTIVES
SECTION | DESCRIPTION | MINIMUM NUMBER OF ELECTIVES REQUIRED AND ELECTIVES SELECTED | |
A105.1 | Waste management | ||
A105.2 | Construction waste landfill maximum | ||
A105.3(1) | Reused, recycled content, recyclable, bio-based and indigenous materials (50percent) | ||
A105.3(2) | Reused, recycled content, recyclable, bio-based and indigenous materials (75percent) | ||
A105.4 | Service life plan | ||
A105.5 | Design for deconstruction and building reuse | ||
A105.6 | Existing building reuse | ||
A105.7 | Historic building reuse |