Strike Section A104.1 (including Subsections 104.1.1 through 104.1.3) of Appendix A of the International Green Construction Code in its entirety without substitution.
Strike Table A104, Site Project Electives, in Appendix A of the International Green Construction Code in its entirety and insert new Table A104 in its place in Appendix A of the Green Construction Code to read as follows:
TABLE A104
SITE PROJECT ELECTIVES
SECTION | DESCRIPTION | MINIMUM NUMBER OF ELECTIVES REQUIRED AND ELECTIVES SELECTED | |
A104.2 | Wildlife corridor | Click to title12_rule 12-k-a04_files_image001.gif view image Yes | |
A104.3 | Infill site | ||
A104.4 | Brownfield site | ||
A104.5 | Site restoration | ||
A104.6 | Mixed use development | ||
A104.7 | Changing and shower facilities | ||
A104.8 | Long-term bicycle parking and storage | ||
A104.9 | Heat island | ||
A104.9.1 | Site hardscape project elective 1 | ||
A104.9.2 | Site hardscape project elective 2 | ||
A104.9.4 | Roof covering project elective - 25 percent vegetative roof coverage | ||
A104.9.4 | Roof covering project elective - 50 percent vegetative roof coverage | ||
A104.9.4 | Roof covering project elective - 75 percent vegetative roof coverage | ||
A104.10 | Native plant landscaping - 75 percent native plants | ||
A104.10 | Native plant landscaping - 100 percent native plants | ||
A104.11 | Electric vehicle charging infrastructure project elective |
Strike Sections A104.7 and A104.8 in Appendix A of the International Green Construction Code in their entirety and substitute new Sections A104.7 and A104.8 in Appendix A of the Green Construction Code in their place to read as follows:
Changing and shower facilities project elective. Projects that provide changing and shower facilities shall receive a project elective.
Long-term bicycle parking and storage project elective. Projects that provide not less than 90 percent of long term bicycle parking within a building or provide the parking with a permanent cover including, but not limited to, roof overhangs, awnings, or bicycle storage lockers, shall be recognized as a single project elective.
Strike Section A104.9 in Appendix A of the International Green Construction Code in its entirety and insert new Section A104.9 in Appendix A of the Green Construction Code in its place to read as follows:
Heat island. Project electives related to heat island impact shall comply with Sections A104.9.1, A104.9.2 or A104.9.4. Compliance with multiple electives shall be recognized.
Strike Section A104.9.3 in Appendix A of the International Green Construction Code in its entirety without substitution.
Strike Section A104.9.4 in Appendix A of the International Green Construction Code in its entirety and insert new Section A104.9.4 in Appendix A of the Green Construction Code in its place to read as follows:
Roof covering project elective. Projects that install vegetative roofs shall be recognized as a project elective. Projects will receive one project elective for 25 percent coverage of total roof square footage, one additional elective credit for 50 percent coverage, or three total elective credits for 75 percent coverage.
Insert new Section A104.10 in Appendix A of the Green Construction Code to read as follows:
Native plant landscaping project elective. Projects that install native plant landscaping beyond the code minimum shall be recognized as a project elective. Projects will receive one project elective for 75 percent native plant landscaping coverage, and an additional project elective for 100 percent coverage.
Insert new Section A104.11 in Appendix A of the Green Construction Code to read as follows:
Electric vehicle charging infrastructure project elective. Projects intending to qualify for an electric vehicle charging infrastructure project elective shall install electric vehicle supply equipment, or electrical infrastructure suitable for the future installation of electric vehicle supply equipment, in accordance the following requirements:
D.C. Mun. Regs. tit. 12, r. 12-K-A04