For the following new sources . . . | You must meet the emission limits for the specified pollutant . . . |
Total fluorides | |
Phosphate Fertilizer Process Line (e.g., Diammonium and/or Monoammonium Phosphate Process Line) | 0.0580 lb/ton of equivalent P2O5 feed. |
Granular Triple Superphosphate Process Line | 0.1230 lb/ton of equivalent P2O5 feed. |
GTSP storage building | 5.0 * 10-4 lb/hr/ton of equivalent P2O5 stored. |
a The new source compliance dates are based on date of construction or reconstruction as specified in § 63.622(a) .
b During periods of startup and shutdown, for emission limits stated in terms of pounds of pollutant per ton of feed, you are subject to the work practice standards specified in § 63.622(d) .
40 C.F.R. 63 app Table 2 to Subpart BB of Part 63