For the following existing sources . . . | You must meet the emission limits for the specified pollutant . . . |
Total fluorides | |
Phosphate Fertilizer Process Line (e.g., Diammonium and/or Monoammonium Phosphate Process Line) | 0.060 lb/ton of equivalent P2O5 feed. |
Granular Triple Superphosphate Process Line | 0.150 lb/ton of equivalent P2O5 feed. |
GTSP storage building | 5.0 * 10-4 lb/hr/ton of equivalent P2O5 stored. |
a The existing source compliance date is June 10, 2002.
b During periods of startup and shutdown, for emission limits stated in terms of pounds of pollutant per ton of feed, you are subject to the work practice standards specified in § 63.622(d) .