40 C.F.R. § 63.1662-63 app Table 9 to Subpart AAAAA of Part 63

Current through May 31, 2024
Appendix Table 9 to Subpart AAAAA of Part 63 - Applicability of General Provisions to Subpart AAAAA

As required in § 63.7140 , you must comply with the applicable General Provisions requirements according to the following table:

Citation Summary of requirementAm I subject to this requirement? Explanations
§ 63.1(a)(1)-(4) ApplicabilityYes
§ 63.1(a)(5) No
§ 63.1(a)(6) ApplicabilityYes
§ 63.1(a)(7)-(a)(9) No
§ 63.1(a)(10)-(a)(14) ApplicabilityYes
§ 63.1(b)(1) Initial Applicability DeterminationYes§§ 63.7081 and 63.7142 specify additional applicability determination requirements.
§ 63.1(b)(2) No
§ 63.1(b)(3) Initial Applicability DeterminationYes
§ 63.1(c)(1) Applicability After Standard EstablishedYes
§ 63.1(c)(2) Permit RequirementsNoArea sources not subject to subpart AAAAA, except all sources must make initial applicability determination.
§ 63.1(c)(3)-(4) No
§ 63.1(c)(5) Area Source Becomes MajorYes
§ 63.1(c)(6) ReclassificationYes
§ 63.1(d) No
§ 63.1(e) Applicability of Permit ProgramYes
§ 63.2 DefinitionsYesAdditional definitions in § 63.7143 .
§ 63.3(a)-(c) Units and AbbreviationsYes
§ 63.4(a)(1)-(a)(2) Prohibited ActivitiesYes
§ 63.4(a)(3)-(a)(5) No
§ 63.4(b)-(c) Circumvention, SeverabilityYes
§ 63.5(a)(1)-(2) Construction/ReconstructionYes
§ 63.5(b)(1) Compliance DatesYes
§ 63.5(b)(2) No
§ 63.5(b)(3)-(4) Construction Approval, ApplicabilityYes
§ 63.5(b)(5) No
§ 63.5(b)(6) ApplicabilityYes
§ 63.5(c) No
§ 63.5(d)(1)-(4) Approval of Construction/ReconstructionYes
§ 63.5(e) Approval of Construction/ReconstructionYes
§ 63.5(f)(1)-(2) Approval of Construction/ReconstructionYes
§ 63.6(a) Compliance for Standards and MaintenanceYes
§ 63.6(b)(1)-(5) Compliance DatesYes
§ 63.6(b)(6) No
§ 63.6(b)(7) Compliance DatesYes
§ 63.6(c)(1)-(2) Compliance DatesYes
§ 63.6(c)(3)-(c)(4) No
§ 63.6(c)(5) Compliance DatesYes
§ 63.6(d) No
§ 63.6(e)(1)(i) General Duty to Minimize EmissionsYes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)
On and after the relevant compliance date for your source as specified in § 63.7083(e) , see § 63.7100 for general duty requirement.
§ 63.6(e)(1)(ii) Requirement to Correct Malfunctions ASAPYes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)
§ 63.6(e)(1)(iii) Operation and Maintenance RequirementsYes
§ 63.6(e)(2) No[Reserved].
§ 63.6(e)(3) Startup, Shutdown Malfunction PlanYes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)
On and after the relevant compliance date for your source as specified in § 63.7083(e) , the OM&M plan must address periods of startup and shutdown. See § 63.7100(d) .
§ 63.6(f)(1) SSM exemptionNoSee § 63.7100 . For periods of startup and shutdown, see § 63.7090(c) .
§ 63.6(f)(2)-(3) Methods for Determining ComplianceYes
§ 63.6(g)(1)-(g)(3) Alternative StandardYes
§ 63.6(h)(1) SSM exemptionNoSee § 63.7100 . For periods of startup and shutdown, see § 63.7090(c) .
§ 63.6(h)(2) Methods for Determining ComplianceYes
§ 63.6(h)(3) No
§ 63.6(h)(4)-(h)(5)(i) Opacity/VE StandardsYesThis requirement only applies to opacity and VE performance checks required in Table 4 to subpart AAAAA.
§ 63.6(h)(5) (ii)-(iii) Opacity/VE StandardsNoTest durations are specified in subpart AAAAA; subpart AAAAA takes precedence.
§ 63.6(h)(5)(iv) Opacity/VE StandardsNo
§ 63.6(h)(5)(v) Opacity/VE StandardsYes
§ 63.6(h)(6) Opacity/VE StandardsYes
§ 63.6(h)(7) COM UseYes
§ 63.6(h)(8) Compliance with Opacity and VEYes
§ 63.6(h)(9) Adjustment of Opacity LimitYes
§ 63.6(i)(1)-(i)(14) Extension of ComplianceYes
§ 63.6(i)(15) No
§ 63.6(i)(16) Extension of ComplianceYes
§ 63.6(j) Exemption from ComplianceYes
§ 63.7(a)(1)-(a)(3) Performance Testing RequirementsYes§ 63.7110 specifies deadlines; § 63.7112 has additional specific requirements.
§ 63.7(b) NotificationYes
§ 63.7(c) Quality Assurance/Test PlanYes
§ 63.7(d) Testing FacilitiesYes
§ 63.7(e)(1) Conduct of TestsYes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)
On and after the relevant compliance date for your source as specified in § 63.7083(e) , see § 63.7112(b) .
§ 63.7(e)(2)-(4) Conduct of TestsYes
§ 63.7(f) Alternative Test MethodYes
§ 63.7(g) Data AnalysisYes
§ 63.7(h) Waiver of TestsYes
§ 63.8(a)(1) Monitoring RequirementsYesSee § 63.7113 .
§ 63.8(a)(2) MonitoringYes
§ 63.8(a)(3) No
§ 63.8(a)(4) MonitoringNoFlares not applicable.
§ 63.8(b)(1)-(3) Conduct of MonitoringYes
§ 63.8(c)(1)(i) CMS Operation/MaintenanceYes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)
On and after the relevant compliance date for your source as specified in § 63.7083(e) , see § 63.7100 for OM&M requirements.
§ 63.8(c)(1)(ii) CMS Spare PartsYes
§ 63.8(c)(1)(iii) Requirement to Develop SSM Plan for CMSYes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)
On and after the relevant compliance date for your source as specified in § 63.7083(e) , no longer required.
§ 63.8(c)(2)-(3) CMS Operation/MaintenanceYes
§ 63.8(c)(4) CMS RequirementsNoSee § 63.7121 .
§ 63.8(c)(4)(i)-(ii) Cycle Time for COM and CEMSYesNo CEMS are required under subpart AAAAA; see § 63.7113 for CPMS requirements.
§ 63.8(c)(5) Minimum COM proceduresYesCOM not required.
§ 63.8(c)(6) CMS RequirementsNoSee § 63.7113 .
§ 63.8(c)(7)-(8) CMS RequirementsYes
§ 63.8(d)(1)-(2) Quality ControlYesSee also § 63.7113 .
§ 63.8(d)(3) Quality ControlYes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)
§ 63.8(e) Performance Evaluation for CMSYesSee also § 63.7113 .
§ 63.8(f)(1)-(f)(5) Alternative Monitoring MethodYes
§ 63.8(f)(6) Alternative to Relative Accuracy Test for CEMSNoNo CEMS required in subpart AAAAA.
§ 63.8(g)(1)-(g)(5) Data Reduction; Data That Cannot Be UsedNoSee data reduction requirements in §§ 63.7120 and 63.7121 .
§ 63.9(a) Notification RequirementsYesSee § 63.7130 .
§ 63.9(b) Initial NotificationsYes
§ 63.9(c) Request for Compliance ExtensionYes
§ 63.9(d) New Source Notification for Special Compliance RequirementsYes
§ 63.9(e) Notification of Performance TestYes
§ 63.9(f) Notification of VE/Opacity TestYesThis requirement only applies to opacity and VE performance tests required in Table 5 to subpart AAAAA. Notification not required for VE/opacity test under Table 7 to subpart AAAAA.
§ 63.9(g) Additional CMS NotificationsNoNot required for operating parameter monitoring.
§ 63.9(h)(1)-(h)(3) Notification of Compliance StatusYes
§ 63.9(h)(4) No
§ 63.9(h)(5)-(h)(6) Notification of Compliance StatusYes
§ 63.9(i) Adjustment of DeadlinesYes
§ 63.9(j) Change in Previous InformationYes
§ 63.9(k) Electronic reporting proceduresYesOnly as specified in § 63.9(j) .
§ 63.10(a) Recordkeeping/Reporting General RequirementsYesSee §§ 63.7131 through 63.7133 .
§ 63.10(b)(1) RecordsYes
§ 63.10(b)(2)(i) Recordkeeping of Occurrence and Duration of Startups and ShutdownsYes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)
§ 63.10(b)(2)(ii) Recordkeeping of Failures to Meet a StandardYes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)
On and after the relevant compliance date for your source as specified in § 63.7083(e) , see § 63.7132 for recordkeeping of (1) date, time and duration; (2) listing of affected source or equipment, and an estimate of the quantity of each regulated pollutant emitted over the standard; and (3) actions to minimize emissions and correct the failure.
§ 63.10(b)(2)(iii) Maintenance RecordsYes
§ 63.10(b)(2)(iv)-(v) Actions Taken to Minimize Emissions During SSMYes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)
On and after the relevant compliance date for your source as specified in § 63.7083(e) , see § 63.7100 for OM&M requirements.
§ 63.10(b)(2)(vi)-(xii) Recordkeeping for CMSYes
§ 63.10(b)(2) (xiii)Records for Relative Accuracy TestNo
§ 63.10(b)(2)(xiv) Records for NotificationYes
§ 63.10(b)(3) Applicability DeterminationsYes
§ 63.10(c) Additional CMS RecordkeepingNoSee § 63.7132 .
§ 63.10(d)(1) General Reporting RequirementsYes
§ 63.10(d)(2) Performance Test ResultsYes
§ 63.10(d)(3) Opacity or VE ObservationsYesFor the periodic monitoring requirements in Table 7 to subpart AAAAA, report according to § 63.10(d)(3) only if VE observed and subsequent visual opacity test is required.
§ 63.10(d)(4) Progress ReportsYes
§ 63.10(d)(5)(i) Periodic Startup, Shutdown, Malfunction ReportsYes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)
On and after the relevant compliance date for your source as specified in § 63.7083(e) , see § 63.7131 for malfunction reporting requirements.
§ 63.10(d)(5)(ii) Immediate Startup, Shutdown, Malfunction ReportsYes before the relevant compliance date for your source as specified in § 63.7083(e)
No on and after the relevant compliance date for your source as specified in § 63.7083(e)
§ 63.10(e) Additional CMS ReportsNoSee specific requirements in subpart AAAAA, see § 63.7131 .
§ 63.10(f) Waiver for Recordkeeping/ReportingYes
§ 63.11(a)-(b) Control Device and Work Practice RequirementsNoFlares not applicable.
§ 63.12(a)-(c) State Authority and DelegationsYes
§ 63.13(a)-(c) State/Regional AddressesYes
§ 63.14(a)-(b) Incorporation by ReferenceNo
§ 63.15(a)-(b) Availability of Information and ConfidentialityYes
§ 63.16 Performance Track ProvisionsYes

40 C.F.R. 63.1662-63 app Table 9 to Subpart AAAAA of Part 63

85 FR 44988, July 24, 2020, as amended at 85 FR 73912, Nov. 19, 2020; 85 FR 84262, Dec. 28, 2020
85 FR 44988, 7/24/2020