Cal. Code Regs. Tit. 27, div. 3, 1, ch. 3, D

Current through Register 2025 Notice Reg. No. 2, January 10, 2025
UST Monitoring Plan

IDELEMENTCODES/CRITERIALENGTHTYPEINFORMATION DESCRIPTIONCERS MINIMALLY REQUIRED FIELDS
1Facility ID Number13ANA facility identifier assigned by the local regulator supporting cross-linking of CERS and local data system records. Because CUPAs do not consistently apply the original regulatory definition of this field (2 AN county 3 AN jurisdiction 6 AN facility number), CERS accepts any alphanumeric string up to 13 characters. The original regulator goals of this field are fulfilled through the CERS ID and CERS System Field "FacilityRegulatorKey" (20.0084).False
1aCERS IDCal/EPA assigned, 8- or 9- digit ID assigned to a specific facility that never has leading zeroes (begins at 10000001). Cal/EPA does not anticipate using 9- digit CERS IDs until the year 2020 or beyond.9NA CERS ID is a Cal/EPA-assigned, 8- or 9- digit ID to uniquely identify a facility in CERS. The CERS ID should remain unchanged across different owners/operators of a facility.False
3Business Name70ANFull legal name of business.True
103Business Site Address70ANStreet address where facility is located. No post office box numbers are allowed. This information must provide a means to geographically locate the facility. The "Supplemental Location Text" field can also be used to capture additional information where the facility's formal address is unclear or not available.True
104City (Business)60ANCity or locality name in which the facility/site is physically located.True
490-3aMonitoring01 = Annually2ANDescribes frequency of service performedTrue
Equipment Serviced99 = Otheron monitoring equipment.
490-3bSpecify Other Frequency of Monitoring Equipment ServiceNarrative15ANDescribes other frequency of service performed on monitoring equipment.False
490-4Site Plot Plan Submitted1 = New Plan Submitted1ANIndicates if a site plan is submitted with this plan or a previously submitted site plan isTrue
2 = Site Plan Previously Submittedcurrent for the facility.
490-5Continuous Electronic TankY = Yes1ANIndicates if continuous tank monitoring is used at the site.False
MonitoringN = No
490-6Tank Secondary01 = Dry2ANDescription of TankFalse
Containment02 = Liquid-Filledsecondary containment
System03 = Pressurizedsystem.
04 = Under Vacuum
490-7Electronic Monitor Panel Manufacturer25ANName of the tank electronic monitor panel.False
490-8Electronic Monitor Panel Model #35ANModel number of electronic monitor panel.False
490-9Leak Sensor Manufacturer20ANName of leak sensor manufacturer.False
490-10Leak Sensor Model #35ANModel number of leak sensorFalse
490-11Automatic Tank GaugingY = Yes1ANIndicates if this type of monitoring (automatic tank gauging) is being performed at theFalse
N = Nosite.
490-12ATG Panel Manufacturer25ANName of ATG panel manufacturerFalse
490-13ATG Model #35ANModel of ATG panelFalse
490-14In-Tank Probe Manufacturer25ANName of ATG in-tank probe manufacturerFalse
490-15In-tank Probe Model #35ANModel number of ATG in-tank probe.False
490-16Tank Leak Test01 = Continuous2ANFrequency of tank leak test.False
Frequency02 = Daily/Nightly
03 = Weekly
04 = Monthly
99 = Other
490-17Other Leak Test FrequencyNarrative10ANOther frequency of tank leak test.False
490-18Programmed01 = 0.1 GPH2ANSensitivity of the programmed leak tests.False
Tank Tests02 = 0.2 GPH
99 = Other
490-19Other Programmed TestsNarrative15ANOther designated sensitivity of programmed leak test.False
490-20Monthly Statistical InventoryY = Yes1ANIndicates if inventory reconciliation is being performed at the site.False
ReconciliationN = No
490-21Weekly Manual Tank GaugeY = Yes1ANIndicates if weekly manual tank gauging is being performed at this site.False
N = No
490-22Tank Gauging01 = 36 Hours2ANLength of time for manual tank gauging period.False
Test Period02 = 60 Hours
490-23Tank Integrity TestingY = Yes1ANIndicates if tank integrity testing is performed at the site.False
N = No
490-24Tank Integrity01 = Annually2ANFrequency of tank integrityFalse
Testing02 = Bienniallytesting.
Frequency99 = Other
490-25Specify Other Tank Integrity Testing FrequencyNarrative15ANFrequency of other tank integrity testing.False
490-26Other MonitoringY = Yes1ANIndicates if another type of monitoring is used at the site, not already indicated.False
N = No
490-27Specify Other MonitoringNarrative100ANSpecifies the other type of monitoring.False
490-28Continuous Monitoring ofY = Yes1ANIndicates if continuous monitoring of the piping secondary containment occurs at the site.False
Piping Secondary ContainmentN = No
490-29Piping Secondary01 = Dry2ANType of piping secondaryFalse
Containment02 = Liquidcontainment.
03 = Pressurized
04 = Under Vacuum
490-30Panel ManufacturerNarrative25ANName of panel manufacturer.False
490-31Panel Model #35ANModel number of panel.False
490-32Leak Sensor ManufacturerNarrative25ANName of leak sensor manufacturer.False
490-33Leak Sensor Model35ANModel of leak sensor.False
490-34Leak Alarm TriggersY = Yes1ANIndicates pump shutdown when a leak alarm occurs.False
Automatic Pump ShutdownN = No
490-35Failure/Disconnect TriggersY = Yes1ANIndicates pump shutdown when failure or disconnect occurs.False
Pump ShutdownN = No
490-36Mechanical Line Leak DetectorY = Yes1ANIndicates that a 3 GPH line mechanical line leak detector is used at the site.False
Performs 3 GPH Leak TestN = No
490-37MLLD ManufacturerNarrative25ANName of leak detector manufacturer.False
490-38MLLD Model35ANModel of leak detector.False
490-39Electronic Line Leak DetectorY = Yes1ANIndicates that an electronic line leak detector (ELLD) is used at the site.False
Performs 3 GPH Leak TestN = No
490-40ELLD ManufacturerNarrative25ANManufacturer of electronic line leak detector (ELLD).False
490-41ELLD Model35ANModel of electronic line leak detector (ELLD).False
490-42ELLD01 = 0.2 GPH2ANType of electronic line leakFalse
Programmed In-Line Testing02 = 0.1 GPHdetector (ELLD) test performed.
490-43ELLD Triggers Automatic PumpY = Yes1ANIndicates if electronic line leak detector (ELLD) triggers automatic pump shutdown.False
ShutdownN = No
490-44ELLD Failure/DisconnectY = Yes1ANIndicates if electronic line leak detector (ELLD) triggers auto-shutdown for failure orFalse
Triggers Automatic ShutdownN = Nodisconnection.
490-45Pipeline Integrity TestingY = Yes1ANIndicates if pipeline integrity testing occurs at the site.False
N = No
490-46Pipeline Integrity01 = Annually2ANFrequency of pipeline integrity testing.False
Testing02 = Every 3 Years
Frequency03 = Other
490-47Specify Other Integrity Testing Frequency10ANOther frequency of pipeline integrity testing.False
490-48Visual Pipeline MonitoringY = Yes1ANIndicates if visual pipeline monitoring occurs at the site.False
N = No
490-49Visual Pipeline01 = Daily2ANFrequency of visual pipelineFalse
Monitoring02 = Weeklymonitoring.
Frequency03 = Minimum Monthly
490-50Suction Piping MeetsY = Yes1ANIndicates if suction piping that meets the criteria is the method to monitor the pipeline.False
Exemption CriteriaN = No
490-51No Regulated Piping PerY = Yes1ANIndicates that any piping connected to the tank system is not regulated under the UST law, orFalse
Health and Safety Code, Division 20, Chapter 6.7 Is Connected To The Tank SystemN = Nothere is no piping connected to the tank system.
490-52Other Pipeline MonitoringY = Yes1ANIndicates if other pipeline monitoring option used at site.False
N = No
490-53Specify Other Pipeline MonitoringNarrative100ANIdentifies other monitoring option.False
490-54aUDC1 = Continuous2ANIndicates type of under dispenser containmentTrue
Monitoring2 = Float and Chain Assembly(UDC) monitoring.
3 = Electronic Standalone
4 = No Dispensers
99 = Other
490-54bSpecify Other UDC MonitoringNarrative15ANIndicates type of other under dispenser containment (UDC) monitoring.False
490-55UDC Panel ManufacturerNarrative25ANManufacturer of under dispenser containment (UDC) panel.False
490-56UDC Panel Model #35ANModel # of under dispenser containment (UDC) panel.False
490-57UDC Leak Sensor ManufacturerNarrative20ANManufacturer of under dispenser containment (UDC) leak sensor.False
490-58UDC Leak Sensor Model35ANModel # of under dispenser containment (UDC) leak sensor.False
490-59Detection of a Leak into theY = Yes1ANIndicates if alarms are triggered when a leak is detected in the under dispenser containmentFalse
UDC Triggers Audible and Visual AlarmsN = No(UDC).
490-60UDC Leak Alarm TriggersY = Yes1ANIndicates if an under dispenser containment (UDC) leak alarm causes automatic pumpFalse
Automatic Pump ShutdownN = Noshutdown.
490-61Failure/Disconnection of UDCY = Yes1ANIndicates if failure or disconnection of the under dispenser containment (UDC) monitoringFalse
Monitoring System Triggers Automatic Pump ShutdownN = Nosystem causes pump shutdown.
490-62UDC Monitoring Stops FlowY = Yes1ANIndicates if the under dispenser containment (UDC) monitor stops the flow of product atFalse
of Product at DispenserN = Nothe dispenser.
490-63UDC1 = Single-walled1ANIndicates the type of underFalse
Construction2 = Double-walleddispenser containment (UDC) construction.
490-64aUDC Secondary01 = Liquid2ANType of under dispenserFalse
Containment02 = Pressurecontainment (UDC)
Monitoring03 = Vacuumsecondary containment monitoring.
490-64bA Leak Within the SecondaryY = Yes1ANIndicates that a leak in the under dispenser containment (UDC) secondary containmentFalse
Containment of UDC Causes Audible and Visual AlarmsN = Nocauses audible and visual alarms.
490-65ELD TestingY = Yes1ANIndicates if tanks are enhanced leak detection (ELD) tested on a periodic basis.False
N = No
490-66Secondary ContainmentY = Yes1ANIndicates if secondary containment testing is conducted every 36 months.False
TestingN = No
490-67Spill Bucket TestingY = Yes1ANIndicates if spill bucket testing is conducted annually.False
N = No
490-68aAlarm LogsY = Yes1ANIndicates that alarm log records are kept for the facility.False
N = No
490-68bVisual Inspection RecordsY = Yes1ANIndicates that visual inspection records are kept for the facility.False
N = No
490-68cTank Integrity Testing ResultsY = Yes1ANIndicates that tank integrity testing results are kept for the facility.False
N = No
490-68dSIR Testing ResultsY = Yes1ANIndicates that statistical inventory reconciliation (SIR) testing results and supportingFalse
N = Nodocumentation records are kept for the facility.
490-68eTank Gauging ResultsY = Yes1ANIndicates that tank gauging results and supporting documentation records are kept for theFalse
N = Nofacility.
490-68fATG Testing ResultsY = Yes1ANIndicates that ATG testing results and supporting documentation records are kept for theFalse
N = Nofacility.
490-68gCorrosion Protection LogsY = Yes1ANIndicates that corrosion protection logs are kept for the facility.False
N = No
490-68hEquipment Maintenance andY = Yes1ANIndicates that equipment maintenance and calibration records are kept for the facility.False
Calibration RecordsN = No
490-69aPersonnel with UST MonitoringY = Yes1ANIndicates that personnel within the facility are familiar with the indicated documents.False
Responsibilities are Familiar with Training DocumentsN = No
490-69bUST Monitoring PlanY = Yes1ANIndicates that facility personnel are familiar with the UST monitoring plan for the facility.False
N = No
490-69cOperating ManualsY = Yes1ANIndicates that facility personnel are familiar with the UST operating manuals for the facility.False
N = No
490-69dCA UST RegulationsY = Yes1ANIndicates that facility personnel are familiar with the California UST regulations.False
N = No
490-69eCA UST LawY = Yes1ANIndicates that facility personnel are familiar with the California UST law.False
N = No
490-69fSWRCB Handbook for TankY = Yes1ANIndicates that facility personnel are familiar with the SWRCB Handbook for Tank Owners -False
Owners - Manual and SIRN = NoManual and SIR.
490-69gSWRCB Publication:Y = Yes1ANIndicates that facility personnel are familiar with the SWRCB Publication: UnderstandingFalse
Understanding Automatic Tank Gauging SystemsN = NoAutomatic Tank Gauging Systems.
490-69hOther Training DocumentsY = Yes1ANIndicates that other training documents are used.False
N = No
490-69iSpecify Other Training DocumentsNarrative100ANList of the other training documents that are used.False
490-70Designated Operator TrainingY = Yes1ANIndicates that the facility has a designated operator and that training will be provided.False
N = No
490-71Comments and Additional InformationNarrative300ANAdditional information to support the application for an operating permit.False
490-72Name of First Person Having Responsibility80ANName of first person having responsibility for monitoring.True
490-73Title of First Person Having Responsibility50ANTitle of first person having responsibility for monitoring.True
490-74Name of Second Person Having Responsibility80ANName of second person having responsibility for monitoring.False
490-75Title of Second Person Having Responsibility50ANTitle of second person having responsibility for monitoring.False
490-76Signature Representation01 = Tank Owner/Operator2ANIndicates who signed the monitoring plan.False
02 = Facility Owner/Operator
03 = Authorized Representative of Owner
490-77Signature DateYYYY-MM-DD10DDate monitoring plan is certified.False
490-78Applicant Name80ANName of applicant signing monitoring plan.False
490-79Applicant Title50ANTitle of applicant signing monitoring plan.False

Cal. Code Regs. Tit. 27, div. 3, 1, ch. 3, D

1. New form filed 12-18-2007; operative 1-17-2008 (Register 2007, No. 51).
2. Amendment filed 12-17-2013; operative 12-17-2013 pursuant to Government Code section 11343.4(b)(3) (Register 2013, No. 51).
1. New form filed 12-18-2007; operative 1-17-2008 (Register 2007, No. 51).
2. Amendment filed 12-17-2013; operative 12-17-2013 pursuant to Government Code section 11343.4(b)(3) (Register 2013, No. 51).