Wyo. Stat. § 41-7-709

Current with changes from the 2024 Legislative Session, Acts 1-58, 60-118
Section 41-7-709 - Determination and apportionment of cost of power portion of project

That if any project or amended project includes plans for the generation of electric energy and power, the board of commissioners shall ascertain the total cost of all of the property and works which are necessary to be used in connection with the generation, sale and distribution of electric energy and power as set forth in the plans of the district, and shall also ascertain what portion of the assessment of benefit to accrue to each tract or parcel of land embraced or to be included within said irrigation district consists of the properties and works which are necessary and required to be so used.

W.S. 41-7-709