Wyo. Stat. § 16-1-204

Current with changes from the 2024 Legislative Session, Acts 1-58, 60-118
Section 16-1-204 - Environmental review process
(a) Through the department the board shall conduct a review of potential environmental impacts of projects receiving assistance from the account. The environmental review process shall:
(i) Contain mechanisms requiring implementation of mitigation measures to ensure the project is environmentally sound;
(ii) Allow the public an opportunity to challenge environmental review determinations and enforcement actions;
(iii) Include documentation of information, processes and premises that influence decisions;
(iv) Require public notice and participation;
(v) Include evaluation criteria and processes allowing consideration of alternative decisions; and
(vi) Comply with the requirements of Title VI and significant issues pertaining to underground storage tanks as specified in Subtitle I of the Resource Conservation and Recovery Act, 42 U.S.C. § 6991 et seq.