Wis. Stat. § 31.23

Current through Acts 2023-2024, ch. 272
Section 31.23 - Forfeitures; private bridges and dams
(1) Every person who constructs or maintains in navigable waters or aids in the construction or maintenance therein of any bridge or dam not authorized by law, shall forfeit for each such offense, and for each day that the free navigation of such waters are obstructed by such bridge or dam a sum not exceeding $50.
(2) Every person or corporation violating any of the provisions of this chapter, other than those mentioned in sub. (1), or violating any order made by the department pursuant to this chapter, shall forfeit for each such violation not more than $1,000.
(3)
(a) There shall be no forfeiture under this section in any case where a bridge is built by a private citizen across any navigable waters having a width of 35 feet or more, providing such bridge does not impair the rights of the public for purposes of navigation or fishing.
(b) No such bridge shall be maintained unless its construction shall first be approved by the department after public hearing and on not less than 10 days' written notice to the applicant and to the county and town clerks of the county and town wherein all or a portion of the proposed bridge is to be located.
(c) Each applicant who shall apply to the department for a permit to construct any such bridge shall state in the application the proposed location of the bridge, the depth of the water to be spanned, the materials to be used in the construction of the bridge, the plans of the proposed bridge, together with such other facts as the department may require.
(d) Every such bridge used by the public shall at all times be maintained in a safe condition by the owners of the land abutting the approaches of the bridge, and the owners shall make such repairs as are reasonably necessary therefor. The town shall not become liable for any damages resulting from the insufficiency or want of repairs of such bridge. If the department upon inspection finds that such bridge is in need of repairs, it shall notify the owners responsible for the repairs thereof, and also send a copy of such notice to the town board, to make all repairs as are reasonably necessary therefor. If such repair work as ordered by the department is not commenced within 60 days after receipt of such notice, the department may close such bridge until it is so repaired. Whenever any owner responsible for such bridge shall fail to repair or maintain the bridge in a good and safe condition, after having been notified so to do by the department for 60 days after such notification, such town board upon its own initiative may make such required repairs on such bridge, and the cost thereof shall be paid by the owners responsible therefor, and the town clerk shall enter such amount of the cost of repairs upon the next tax roll of the town.
(e) This subsection does not apply to a bridge that is constructed, maintained, or operated in association with mining or bulk sampling that is subject to subch. III of ch. 295.

Wis. Stat. § 31.23

Amended by Acts 2013 ch, 1,s 26, eff. 3/26/2013.
1991 a. 316.

Sub. (1) provides no substantive rule for which a violation would initiate the abatement procedures under s. 31.25. The remedy provided is limited to the forfeiture provided under sub. (1). Capt. Soma Boat Line, Inc. v. Wisconsin Dells, 56 Wis. 2d 838, 203 N.W.2d 369 (1973).