Wis. Stat. § 291.13

Current through Acts 2023-2024, ch. 272
Section 291.13 - Capacity assurance plan revision and review
(1) In this section, "capacity assurance plan" means the plan submitted under 42 USC 9604(c) (9) for the management of hazardous waste generated in this state.
(2) The department shall do all of the following:
(a) Monitor changes in the generation of hazardous waste in this state and the progress toward meeting the goals in the capacity assurance plan.
(b) Notify the governor of any significant problems that occur or may occur in the ability to manage a type of hazardous waste in this state and of the need to change the goals in the capacity assurance plan.
(c) Each year in which submission of a revised capacity assurance plan is required by the federal environmental protection agency, at least 75 days before the federal environmental protection agency deadline for submittal, complete a draft of a revised capacity assurance plan and provide the draft to the governor and the legislature under s. 13.172(2).
(d) Hold a public informational hearing, that is not a contested case hearing under ch. 227, to solicit comments on the draft of the revised capacity assurance plan no later than 45 days after providing the draft under par. (c).
(e) Each year in which submission of a revised capacity assurance plan is required by the federal environmental protection agency, provide its proposed version of the revised capacity assurance plan, no later than 14 days prior to the federal environmental protection agency deadline for submittal, to the governor and the legislature under s. 13.172(2).

Wis. Stat. § 291.13

1989 a. 325; 1991 a. 41; 1995 a. 27; 1995 a. 227 s. 697; Stats. 1995 s. 291.13.