Wis. Stat. § 88.81

Current through Acts 2023-2024, ch. 272
Section 88.81 - Proceedings to suspend operations of drainage district
(1)
(a) The owners of land representing 90 percent or more of the confirmed benefits in a drainage district, excluding benefits received by land owned by this state, may file with the drainage board a petition requesting that the board conduct no further proceedings and incur on behalf of the district no further expense if the petition is filed within 2 years after the order organizing the district is issued under s. 88.34.
(b) The owners of land representing 67 percent or more of the confirmed benefits in a drainage district, excluding benefits received by land owned by this state, may file with the drainage board a petition requesting that the board conduct no further proceedings and incur on behalf of the district no further expense if the petition is filed at least 2 years after the order organizing the district is issued under s. 88.34.
(bm) Except as provided in par. (bs), the owner of any land in a drainage district may file with the drainage board a petition requesting that the board conduct no further proceedings and incur on behalf of the district no further expense if the petition is filed at least 20 years after the latest assessment for costs against land in the drainage district.
(bs) A state agency, as defined in s. 16.61(2) (d), may not petition for the suspension of operations of a drainage district.
(c) Upon receipt of a petition, the drainage board shall fix a time and place of a hearing on the petition and shall cause notice of the hearing to be given under s. 88.05(2) (b) to the persons specified in s. 88.05(4) (b).
(2) If after the hearing the drainage board finds that the petition is signed by the required number of owners, that notice of the hearing was properly given, and that the conditions of sub. (3) have been met, it shall issue an order directing that no more work be done in or expense incurred on behalf of the district. The order does not dissolve the district or in any way affect existing contracts. The district remains liable for all its debts existing at the time of issuance of the drainage board order suspending operations, and the board shall continue to levy such additional assessments for costs as are necessary to meet existing obligations.
(3) As a condition of issuing the order under sub. (2), the drainage board shall require the petitioners under this section to pay the expenses of the hearing under this section and all expenses, if any, incurred in connection with specific current projects whose completion would be affected by the drainage board order.
(4) An order suspending operations of a drainage district remains in effect until a like application upon like notice requesting that work be continued is heard and determined in favor of petitioners.
(5) Subsections (1) to (3) do not apply on or after July 14, 2015.

Wis. Stat. § 88.81

Amended by Acts 2015 ch, 55,s 2596g, eff. 7/14/2015.
1977 c. 449; 1983 a. 483; 1993 a. 456.