Current through the 2024 Fourth Special Session
Section 73-28-402 - Agreement for delivery - Period for repayment of costs(1) The board and each district shall establish by contract the timing and amount of developed water to be delivered to the district.(2) If a contract was made before the project's completion, the district shall repay the preconstruction and construction costs within 50 years from the date of: (a) the delivery of developed water to the district during the first 10 years after the project is completed; or(b) the project's completion for any developed water delivered to the district after the tenth anniversary date of the project's completion.(3) If a contract was made after the project's completion date, the district shall repay the preconstruction and construction costs within a period not to exceed 50 years from the date that the contract was made.(4) The board shall establish and charge a reasonable interest rate for the unpaid balance of reimbursable preconstruction and construction costs.Enacted by Chapter 216, 2006 General Session.