In conducting a feasibility study for a project (or a component of a project) for ecosystem restoration, the Secretary shall ensure that the recommended project includes, as an integral part of the project, a plan for monitoring the success of the ecosystem restoration.
The monitoring plan shall-
For a period of 10 years from completion of construction of a project (or a component of a project) for ecosystem restoration, the Secretary shall consider the cost of carrying out the monitoring as a project cost. If the monitoring plan under subsection (b) requires monitoring beyond the 10-year period, the cost of monitoring shall be a non-Federal responsibility.
A monitoring plan under subsection (b) shall include a description of-
The responsibility of a non-Federal interest for operation and maintenance of the nonstructural and nonmechanical elements of a project, or a component of a project, for ecosystem restoration shall cease 10 years after the date on which the Secretary makes a determination of success under subsection (b)(2).
The Secretary is not responsible for the operation or maintenance of any components of a project with respect to which a non-Federal interest is released from obligations under subsection (e).
33 U.S.C. § 2330a
EDITORIAL NOTES
CODIFICATIONSection was enacted as part of the Water Resources Development Act of 2007, and not as part of the Water Resources Development Act of 1986 which comprises this chapter.
AMENDMENTS2016-Subsecs. (d) to (f). Pub. L. 114-322 added subsecs. (d) to (f).
STATUTORY NOTES AND RELATED SUBSIDIARIES
"SECRETARY" DEFINED Secretary means the Secretary of the Army, see section 2 of Pub. L. 110-114 set out as a note under section 2201 of this title.