Section 3222 - Independent cost estimate required before approval
(a) REQUIREMENT.- A milestone decision authority may not approve entering a milestone phase of a major defense acquisition program or major subprogram unless an independent cost estimate has been conducted or approved by the Director of Cost Assessment and Program Evaluation and considered by the milestone decision authority that-
(1) for the technology maturation and risk reduction phase, includes the identification and sensitivity analysis of key cost drivers that may affect life-cycle costs of the program or subprogram; and
(2) for the engineering and manufacturing development phase, or production and deployment phase, includes a cost estimate of the full life-cycle cost of the program or subprogram.
(b) REGULATIONS.-The regulations governing the content and submission of independent cost estimates required by section 3221 of this title shall require that the independent cost estimate of the full life-cycle cost of a program or subprogram include-
(1) all costs of development, procurement, military construction, operations and support, and trained manpower to operate, maintain, and support the program or subprogram upon full operational deployment, without regard to funding source or management control; and
(2) an analysis to support decisionmaking that identifies and evaluates alternative courses of action that may reduce cost and risk, and result in more affordable programs and less costly systems.

10 U.S.C. § 3222

Added and amended Pub. L. 116-283, div. A, title XVIII, §1812(a), (c), Jan. 1, 2021, 134 Stat. 4174, 4175.

EDITORIAL NOTES

CODIFICATIONThe text of subsec. (b) of section 2334 of this title, which was transferred to this section and amended by Pub. L. 116-283, §1812(c), was based on Pub. L. 114-328, div. A, title VIII, §842(a)(4), Dec. 23, 2016, 130 Stat. 2288.

PRIOR PROVISIONSA prior section 3222, act Aug. 10, 1956, ch. 1041, 70A Stat. 176; Pub. L. 96-513, title V, §502(7), Dec. 12, 1980, 94 Stat. 2909, related to authorized strength of Army Reserve, exclusive of members on active duty, prior to repeal by Pub. L. 103-337, div. A, title XVI, §§1662(a)(3), 1691, Oct. 5, 1994, 108 Stat. 2988, 3026, effective Dec. 1, 1994. See section 12002(a) of this title.

AMENDMENTS2021-Subsec. (a). Pub. L. 116-283, §1812(c)(1), (2)(A), (D), redesignated subsec. (b) of section 2334 of this title as subsec. (a) of this section, substituted "Requirement" for "Independent Cost Estimate Required Before Approval" in heading, struck out par. (1) designation before "A milestone", and redesignated subpars. (A) and (B) as pars. (1) and (2), respectively.Subsec. (b). Pub. L. 116-283, §1812(c)(2)(B) -(D), redesignated subsec. (a)(2) as (b), inserted heading, substituted "section 3221 of this title" for "subsection (a)" in introductory provisions, and redesignated subpars. (A) and (B) as pars. (1) and (2), respectively.

STATUTORY NOTES AND RELATED SUBSIDIARIES

EFFECTIVE DATESection and amendment by Pub. L. 116-283 effective Jan. 1, 2022, with additional provisions for delayed implementation and applicability of existing law, see section 1801(d) of Pub. L. 116-283, set out as an Effective Date of 2021 Amendment note preceding section 3001 of this title.

includes
"includes" means "includes but is not limited to"; and
active duty
The term "active duty" means full-time duty in the active military service of the United States, including sustained duty in the Space Force. Such term includes full-time training duty, annual training duty, and attendance, while in the active military service, at a school designated as a service school by law or by the Secretary of the military department concerned. Such term does not include full-time National Guard duty.
authorized strength
The term "authorized strength" means the largest number of members authorized to be in an armed force, a component, a branch, a grade, or any other category of the armed forces.