Current with legislation from the 2023 Regular and Special Sessions signed by the Governor as of November 21, 2023.
Section 121.452 - Applicability This subchapter does not apply to:
(1) an extension of an existing sour gas pipeline facility that is in compliance with the railroad commission's rules for oil, gas, or geothermal resource operation in a hydrogen sulfide area if: (A) the extension is not longer than five miles;(B) the nominal pipe size is not larger than six inches in diameter; and(C) the railroad commission is given notice of the construction of the extension not later than 24 hours before the start of construction;(2) a new or an extension of a low-pressure gathering system; or(3) an interstate gas pipeline facility, as defined by 49 U.S.C. Section 60101 and its subsequent amendments or a succeeding law, that is used for the transportation of sour gas.Tex. Util. Code § 121.452
Amended by: Acts 2013, 83rd Leg., R.S., Ch. 1177 (S.B. 901), Sec. 12, eff. September 1, 2013Added by Acts 1999, 76th Leg., ch. 62, Sec. 18.13(a), eff. Sept. 1, 1999.