Tex. Util. Code § 39.166

Current with legislation from the 2023 Regular and Special Sessions signed by the Governor as of November 21, 2023.
Section 39.166 - Reliability Plan For Regions With Rapid Electrical Load Growth
(a) The commission shall direct the independent organization certified under Section 39.151 for the ERCOT power region to:
(1) identify each region in which transmission capacity is insufficient to meet the region's existing and forecasted electrical load, as reasonably determined by the certificated transmission service provider; and
(2) develop a reliability plan to serve existing and forecasted electrical load in the identified region.
(b) The commission shall develop a plan to implement each reliability plan adopted under Subsection (a) to ensure timely development and approval of necessary transmission service improvements.

Tex. Util. Code § 39.166

Added by Acts 2023, Texas Acts of the 88th Leg.- Regular Session, ch. 892,Sec. 3, eff. 6/13/2023.