Current with legislation from the 2023 Regular and Special Sessions signed by the Governor as of November 21, 2023.
Section 283.202 - Costs and Expenses(a) The cost of the project may include:(1) the cost of construction;(2) the cost of all property used in the construction, acquisition, improvement, operation, or maintenance of the project;(3) payment of the cost of condemning property, including the award, court costs, and attorney's fees;(4) payment of all legal, fiscal, or engineering expenses incurred in the acquisition or construction of the project, the making of any preliminary survey or investigation, or the authorization and issuance of the bonds; and(5) payment of interest on the bonds before construction, during construction, and for one year after construction of the project.(b) Any preliminary expense paid from a county fund shall be repaid to the fund from the proceeds of the bonds when available.Tex. Transp. Code § 283.202
Acts 1995, 74th Leg., ch. 165, Sec. 1, eff. Sept. 1, 1995.