S.D. Codified Laws § 34-53-6

Current through the 2024 Legislative Session
Section 34-53-6 - [Repealed effective 6/30/2025] Time for submission and approval of claim or request for pre-approval

A claim under § 34-53-3 may be submitted to the director only after the project commencement date. A request under § 34-53-4 may be submitted on or after March 27, 2019.

A claim under § 34-53-3 shall be submitted to the director within forty-five days of the date the extraordinary expense is incurred.

Notwithstanding any other provision of this chapter, the director may not approve any claim or any request for pre-approval that will not be incurred within one year after the project completion date, subject to § 34-53-16.

SDCL 34-53-6

SL 2019, ch 157, §6, eff. Mar. 27, 2019.
Added by S.L. 2019, ch. 157,s. 6, eff. 3/27/2019.

This section is repealed effective June 30, 2025 pursuant to SL 2019, ch 157, §19.