S.D. Codified Laws § 34-29A-26
Current through the 2024 Legislative Session
Each boiler used or proposed to be used within this state, except boilers exempt under § 34-29A-14, shall be thoroughly inspected as to their construction, installation and condition as follows:
A grace period of two months beyond the periods specified in subdivisions (1), (2), and (3) of this section may elapse between certificate inspections. The chief inspector may, at his discretion, permit longer periods between certificate inspections.
SDCL 34-29A-26