Neb. Rev. Stat. §§ 37-1729

Current with changes from the 2024 Legislative Session
Section 37-1729 - Commission; duties; powers
(1) Before the construction manager begins any construction services, the commission shall:
(a) Conduct an independent cost estimate for the project; and
(b) Conduct contract negotiations with the construction manager to develop a construction manager-general contractor contract for construction services.
(2) If the construction manager and the commission are unable to negotiate a contract, the commission may use other contract procurement processes as provided by law. Persons or organizations who submitted proposals but were unable to negotiate a contract with the commission shall be eligible to compete in the other contract procurement processes.

Neb. Rev. Stat. §§ 37-1729

Laws 2018, LB 775, § 30.
Added by Laws 2018, LB 775,§ 30, eff. 7/19/2018.