Wash. Rev. Code § 77.125.060

Current through the 2024 Regular Session
Section 77.125.060 - Facility operator must hire marine engineering firm to conduct inspections
(1) For marine finfish aquaculture, the facility operator must hire, at their own expense, a marine engineering firm approved by the department to conduct inspections. Inspections must occur approximately every two years, when net pens are fallow, and must include topside and mooring assessments related to escapement potential, structural integrity, permit compliance, and operations.
(2) Any net pen facility must be found to be in good working order to receive fish.
(3) If the facility is found to be in imminent danger of collapse or release of finfish, the director may require the operator to remove fish or deny a fish transfer permit.

RCW 77.125.060

Added by 2018 c 179,§ 12, eff. 6/7/2018.