Wash. Rev. Code § 39.10.250

Current through Chapter 376 of the 2024 Regular Session
Section 39.10.250 - Project review committee-Duties

The committee shall:

(1) Certify, or renew certification for, public bodies to use design-build or general contractor/construction manager contracting procedures, or both;
(2) Review and approve the use of the design-build or general contractor/construction manager contracting procedures on a project by project basis for public bodies that are not certified under RCW 39.10.270;
(3) Review and approve the use of alternative subcontractor selection under RCW 39.10.385 on a project-by-project basis for public bodies that are not certified under RCW 39.10.270, which review and approval may be concurrent with project approval; and
(4) Review and approve not more than two design-build demonstration projects that include procurement of operations and maintenance services for a period longer than three years.

RCW 39.10.250

Amended by 2021 c 230,§ 5, eff. 5/10/2021.
Amended by 2019 c 212,§ 2, eff. 7/28/2019.
Amended by 2013 c 222,§ 5, eff. 6/30/2013.
2009 c 75 § 2; 2007 c 494 § 105.

Sunset Act application: See note following chapter digest.

Effective date- 2021 c 230 : See note following RCW 39.10.210.

Effective date- 2013 c 222 : See note following RCW 39.10.210.