Okla. Stat. tit. 61 § 113.1

Current through Laws 2024, c. 453.
Section 113.1 - [Multiple versions] Partial Payment - Retainage
A. A public construction contract shall provide for partial payment based upon work completed. The contract shall provide that up to five percent (5%) of all partial payments made shall be withheld as retainage until the project is fifty percent (50%) complete as determined by the awarding agency. When the awarding public agency determines that the project is at least fifty percent (50%) complete, the retainage amount shall be two and one- half percent (2.5%) with respect to the balance of the work.
B. The Department of Transportation or the Oklahoma Turnpike Authority shall not withhold retainage on public construction contracts awarded by the Department or the Authority.
C. The Department of Transportation shall not withhold retainage or require any bond on projects awarded to railroads on the railroad's privately owned or operated rail property.

Okla. Stat. tit. 61, § 113.1

Amended by Laws 2022 , c. 238, s. 24, eff. 11/1/2022.
Added by Laws 1977, SB 65, c. 74, § 2, eff. 10/1/1977; Amended by Laws 1983, HB 1305, c. 67, § 1, emerg. eff. 4/29/1983; Amended by Laws 1995, SB 250, c. 200, § 2, emerg. eff. 5/19/1995; Amended by Laws 1997, SB 210, c. 278, § 4, emerg. eff. 5/27/1997; Amended by Laws 2006 , SB 558, c. 271, § 19, emerg. eff. 7/1/2006; Amended by Laws 2011 , HB 1075, c. 99, § 1, eff. 11/1/2011.
This section is set out more than once due to postponed, multiple, or conflicting amendments.