Current through Laws 2024, c. 453.
Section 202.1 - Design-build and at-risk construction management project delivery methods - Authorization required - ExemptionsA. The design-build and construction management project delivery methods shall not be used without the written approval of the Director of the Office of Management and Enterprise Services, or the Director's designee, when those projects are constructed for a state agency or by an act of the Legislature specifying design-build or at-risk construction management for a project. In all instances where the design-build project or at-risk construction management delivery method is authorized, construction administration shall be performed by the State Facilities Director, the SFD's designee or designees, or otherwise by contract or contract provision approved by the Director of the Office of Management and Enterprise Services for construction administration by another party.B. The use of design-build and construction management project delivery methods shall not interfere or inhibit the opportunity for subcontractors and trade contractors to openly and freely compete for subcontracts or trade contracts pursuant to the Public Competitive Bidding Act of 1974. The State Facilities Director, or designee, or the construction manager shall make the subcontracting and supply opportunities publicly known, as follows:1. Whenever the estimated cost of the contract exceeds Fifty Thousand Dollars ($50,000.00), public notice shall be given by publication in a newspaper of general circulation and published in the county where the work, or the major part of the work, is to be done. Such notice by publication shall be published in two consecutive weekly issues of the newspaper, with the first publication thereof to be at least twenty-one (21) days prior to the date set for opening bids; and2. Notice thereof shall be sent to one in-state trade or construction publication for the publication's use and information whenever the estimated cost of the contract exceeds Fifty Thousand Dollars ($50,000.00); provided, however, this section shall not be construed to require the publication of such notice in such trade or construction publication or to require the provision of such notice to more than one in-state trade or construction publication or to any out-of-state trade or construction publication.C. Bids shall be publicly opened at the time and place designated in the public notice. A representative of the State Facilities Director shall be present at the bid opening.D. The provisions of subsection A of this section shall not apply to projects by contract pursuant to an interagency agreement under Section 581 of Title 74 of the Oklahoma Statutes or to projects a state agency performs solely with the staff of the agency.E. The Office of Management and Enterprise Services shall, pursuant to the Administrative Procedures Act, promulgate rules to effect procedures, processes and design-build/construction management fee guidelines necessary to the fulfillment of its responsibilities under this section.Okla. Stat. tit. 61, § 202.1
Amended by Laws 2019 , c. 299, s. 7, eff. 1/1/2020.Amended by Laws 2013 , c. 302, s. 8, eff. 11/1/2013. Laws 2000 , HB 1250, c. 365, § 2, emerg. eff. 6/6/2000; Amended by Laws 2003 , SB 246, c. 277, § 1, emerg. eff. 7/1/2003; Amended by Laws 2005 , HB 1564, c. 79, § 1, eff. 11/1/2005; Amended by Laws 2006 , SB 558, c. 271, § 28, emerg. eff. 7/1/2006; Amended by Laws 2012 , HB 3079, c. 304, § 319.