Current with legislation from 2024 received as of August 15, 2024.
Section 4926.21 - Make ready work compliance and costs; annual recurring pole attachment fee(A) A provider and an electric cooperative shall comply with the process for make-ready work under 47 U.S.C. 224 and the federal communications commission orders and regulations implementing that section, unless, pursuant to section 4926.57 of the Revised Code, a court of common pleas establishes a different process for make-ready work.(B) The cooperative shall provide a good-faith estimate for any make-ready work, which shall include pole replacement if necessary. All make-ready costs shall be based on the cooperative's actual costs not recovered through the annual recurring attachment rate. The cooperative shall provide detailed documentation of the actual costs.(C) A cooperative that charges an annual recurring attachment fee shall establish the fee in accordance with the cable pole attachment rate formula established in 47 U.S.C. 224(d) and commission orders and regulations implementing that formula, unless, pursuant to section 4926.57 of the Revised Code, a court of common pleas establishes a different attachment fee.Added by 134th General Assembly, HB 2,§1, eff. 5/17/2021.