"EXCESS COSTS
IF AT ANY TIME A HOME CONSTRUCTION SERVICE REQUIRES EXTRA COSTS ABOVE THE COST SPECIFIED OR ESTIMATED IN THE CONTRACT THAT WERE REASONABLY UNFORESEEN, BUT NECESSARY, AND THE TOTAL OF ALL EXTRA COSTS TO DATE EXCEEDS FIVE THOUSAND DOLLARS OVER THE COURSE OF THE ENTIRE HOME CONSTRUCTION CONTRACT, YOU HAVE A RIGHT TO AN ESTIMATE OF THOSE EXCESS COSTS BEFORE THE HOME CONSTRUCTION SERVICE SUPPLIER BEGINS WORK RELATED TO THOSE COSTS. INITIAL YOUR CHOICE OF THE TYPE OF ESTIMATE YOU REQUIRE:
_____ written estimate _____ oral estimate"
R.C. § 4722.02