N.M. Stat. § 47-6-27.2

Current through 2024, ch. 69
Section 47-6-27.2 - Approval necessary for utility connection

Any water, sewer, electric or gas utility that connects service to individual parcels within a subdivision, before a final plat for the subdivision has been approved by the board of county commissioners or before the landowner holds a valid building permit, may be fined a civil penalty of up to five hundred dollars ($500) by the board of county commissioners. The board of county commissioners may also require any utility connected in violation of this section to be disconnected.

NMS § 47-6-27.2

Laws 1995, ch. 212, § 25.