Current through 82nd (2023) Legislative Session Chapter 535 and 34th (2023) Special Session Chapter 1 and 35th (2023) Special Session Chapter 1
Section 338.1691 - Qualifications for construction manager at risk To qualify to enter into contracts with a public body for preconstruction services and to construct a public work, a construction manager at risk must:
1. Not have been found liable for breach of contract with respect to a previous project, other than a breach for legitimate cause, during the 5 years immediately preceding the date of the advertisement for proposals pursuant to NRS 338.1692;2. Not have been disqualified from being awarded a contract pursuant to NRS 338.017, 338.13895, 338.1475 or 408.333;3. Not have entered into a contract with a public body to act as a construction manager as agent during the 4 years immediately preceding the date of the advertisement for proposals pursuant to NRS 338.1692;4. Be licensed as a contractor pursuant to chapter 624 of NRS; and5. If the project is for the construction of a public work of the State, be qualified to bid on a public work of the State pursuant to NRS 338.1379.Added to NRS by 2007, 2891; A 2009, 438; 2011, 3694; R 2013, 2986; R 2017, 4035; A 2021, 736, 2217, 2218Amended by 2021, Ch. 371,§3, eff. 6/4/2021.Amended by 2021, Ch. 371,§1, eff. 6/4/2021.Amended by 2021, Ch. 165,§4, eff. 5/27/2021.Repealed by 2013, Ch. 487,§14.7, eff. 7/1/2017.Added to NRS by 2007, 2891; A 2009, 438; 2011, 3694