Mont. Code § 28-2-723

Current through the 2023 Regular Session
Section 28-2-723 - Construction contracts requiring lien or bond waiver void

A construction contract may not contain provisions requiring a contractor, subcontractor, or material supplier to waive the right to a construction lien or a right to a claim against a payment bond before the contractor, subcontractor, or material supplier has been paid for the labor, materials, or both labor and materials, furnished by the contractor, subcontractor, or material supplier.

§ 28-2-723, MCA

En. Sec. 1, Ch. 119, L. 1999.