Minn. Stat. § 161.3414

Current through 2024, c. 127
Section 161.3414 - DETERMINATION TO USE DESIGN-BUILD SELECTION METHOD
Subdivision 1.General criteria.

A design-build contracting procedure authorized under sections 161.3410 to 161.3426 may be used for a specific project only after the commissioner determines that awarding a design-build contract will serve the public interest.

Subd. 2.Specific criteria.

The commissioner shall use the following criteria as the minimum basis for determining when to use the design-build method of project delivery:

(1) the extent to which it can adequately define the project requirements in a proposed scope of the design and construction desired;
(2) the time constraints for delivery of the project;
(3) the capability and experience of potential contractors with the design-build method of project delivery or similar experience;
(4) the suitability of the project for use of the design-build method of project delivery with respect to time, schedule, costs, and quality factors;
(5) the capability of the Department of Transportation to manage the project, including the employment of experienced personnel or outside consultants;
(6) the capability of the Department of Transportation to oversee the project with individuals or design-build firms who are familiar and experienced with the design-build method of project delivery or similar experience;
(7) the lack of ability and availability of any current state employee to perform the services called for by the contract;
(8) the original character of the product or the services;
(9) the work to be performed on the project is necessary to the agency's achievement of its statutory responsibilities and there is statutory authority to enter into the contract; and
(10) other criteria the commissioner deems relevant and states in writing in its determination to utilize the design-build method of project delivery.

Minn. Stat. § 161.3414

1Sp2001 c 8 art 3 s 3; 2014 c 227 art 2 s 5

Amended by 2014 Minn. Laws, ch. 227,s 2-5, eff. 8/1/2014.