For any project under this section with a cost in excess of $1,500,000, unless the board determines that an emergency exists, the board must notify the chair of the Finance Committee of the senate, and the chairs of the Ways and Means Committee and the Capital Investment Committee of the house of representatives in writing before incurring any contractual obligations.
Plans and specifications must be accompanied by a detailed statement of the cost, quality, and description of all material and labor required for the completion of the work. No plan may be adopted, and no improvement made or building constructed, that contemplates the expenditure for its completion of more money than the appropriation for it, unless otherwise provided by law.
In contracting for projects, the board must not restrict its access to litigation or limit its methods of redress to arbitration or other nonjudicial procedures.
Minn. Stat. § 136F.64
1994 c 532 art 7 s 8; 1995 c 212 art 4 s 43, 44; 2000 c 492 art 1 s 55; 2008 c 179s 42; 2014 c 149 s 74