Mich. Comp. Laws § 324.5412

Current through Public Act 64 of the 2024 Legislative Session
Section 324.5412 - Bypassed projects
(1) The department may bypass projects that fail to meet the schedule negotiated and agreed upon between the water supplier and the department, or that do not have approved planning documents and specifications and an approvable application 90 days before the last day of the state fiscal year, whichever comes first.
(2) A water supplier may submit a written request to the department to extend a project schedule for not more than 60 days. The request must provide the reason for the noncompliance with the schedule. A water supplier may file 1 additional 30-day extension request to its schedule.
(3) A project bypassed under this section must not be considered for an order of approval until all other projects have either been funded or rejected. This section does not prohibit the inclusion of the project in the priority list of the next annual funding cycle or the resubmission of an application for assistance in the next annual funding cycle.
(4) The department shall provide affected water suppliers with a written notice of intent to bypass not less than 30 days before the bypass action.
(5) For projects bypassed under this section, the department shall transmit to the water supplier an official notice of bypass for the fundable project.
(6) A bypass action under this section does not modify any compliance dates established under a permit, order, or other document issued by the department or entered as part of an action brought by this state or a federal agency.
(7) After a project is bypassed, the department may award assistance to projects outside the fundable range. Assistance must be made available to projects outside the fundable range in priority order contingent upon the water supplier's satisfaction of all applicable requirements for assistance within the time period established by the department, but not to exceed 60 days from the date of notification. The department shall notify water suppliers with projects outside the fundable range of bypass action, of the amount of bypassed funds available for obligation, and of the deadline for submittal of a complete, approvable application.

MCL 324.5412

Amended by 2022, Act 132,s 26, eff. 6/30/2022.
Add. 1997, Act 26, Imd. Eff. 6/17/1997.