Mich. Comp. Laws § 125.1562

Current through Public Act 148 of the 2024 Legislative Session
Section 125.1562 - Construction contract; designation of person to submit written requests for progress payments; designation of person to whom requests for progress payments to be submitted; manner and times of submissions; deferring the processing of progress payments; payment of requested progress payment; failure of public agency to make timely progress payment; interest
(1) The construction contract shall designate a person representing the contractor who will submit written requests for progress payments, and a person representing the public agency to whom request for progress payments are to be submitted. The written requests for progress payments shall be submitted to the designated person in a manner and at such times as provided in the construction contract.
(2) The processing of progress payments by the public agency may be deferred by the public agency until work having a prior sequence, as provided in the contract documents, is in place and is approved.
(3) Each progress payment requested, including reasonable interest if requested under subsection (4), shall be paid within 1 of the following time periods, whichever is later:
(a) Thirty days after the architect or professional engineer has certified to the public agency that work is in place in the portion of the facility covered by the applicable request for payment in accordance with the contract documents.
(b) Fifteen days after the public agency has received the funds with which to make the progress payment from a department or agency of the federal or state government, if any funds are to come from either of those sources.
(4) Upon failure of a public agency to make a timely progress payment pursuant to this section, the person designated to submit requests for progress payments may include reasonable interest on amounts past due in the next request for payment.

MCL 125.1562

1980, Act 524, Eff. 1/1/1983.