[2009, c. 293, §5(AMD).]
[1995, c. 287, §8(AMD).]
The department may grant a variance from the provisions of this paragraph upon consultation with the public water supply affected by the excavation. The department may not grant a waiver from the provisions of paragraph A, B or D. [2007, c. 297, §5(AMD).]
The department may grant a variance allowing excavation between 2 and 5 feet of the seasonal high water table. The separation distance requirements described in paragraphs A, B and C do not apply when the private water supply or public drinking water source is owned by the owner of the excavation site.
[2007, c. 297, §§5, 6(AMD).]
The medium borrow pit owner or operator may not further excavate in areas where gravel had been extracted to a level less than 5 feet above, at or below the seasonal high water table unless a variance is granted by the department.
[1997, c. 603, §6(AMD).]
[1995, c. 700, §24(AMD).]
[1995, c. 287, §10(RP).]
For purposes of this subsection, the width of a natural buffer strip is measured from the upland edge of floodplain wetlands; if no floodplain wetlands are present, the width of the natural buffer strip is measured from the normal high-water mark of a great pond, river, stream or brook or the upland edge of a freshwater or coastal wetland. The department may allow excavation to occur under this subsection as long as a permit is obtained pursuant to article 5-A. An excavation is not eligible for a permit by rule under department rules regarding activities adjacent to a protected natural resource.
[2007, c. 616, §4(AMD).]
[1995, c. 287, §12(RP).]
Except for paragraph B, the department may not grant a variance from the provisions of this subsection. The department may grant a variance from paragraph B if the variance will not result in the natural buffer strip being reduced to less than 50 feet between the working edge of the excavation and any road or right-of-way, whichever is farther from the excavation, and if the owner or operator installs visual screening and safety measures as required by the department.
A distance specified in this subsection is measured from the outside edge of the shoulder of the road or edge of the right-of-way unless otherwise specifically provided.
[2005, c. 158, §4(AMD).]
The owner or operator of a medium borrow pit shall install visual screening and safety measures as required by the department. [1997, c. 364, §21(NEW).]
[1997, c. 364, §21(NEW).]
[2005, c. 158, §4(AMD).]
The department may grant a variance from this subsection, except for paragraphs C, D, E and F. Areas are not considered "naturally internally drained" if surface discharge is impeded through the use of structures such as detention ponds, retention ponds and undersized culverts.
[2005, c. 561, §2(AMD).]
[2007, c. 507, §1(AMD).]
[1995, c. 700, §24(RP).]
[1999, c. 468, §16(AMD).]
[1995, c. 700, §24(AMD).]
[2005, c. 158, §6(AMD).]
The department may require a bond payable to the State with sureties satisfactory to the department or such other security as the department may determine adequately secures compliance with this article, conditioned upon the faithful performance of the requirements set forth in this article. Other security may include a security deposit with the State, an escrow account and agreement, insurance or an irrevocable trust. In determining the amount of the bond or the security, the department shall take into consideration the character and nature of the overburden, the future suitable use of the land involved and the cost of grading and reclamation required. All proceeds of forfeited bonds or other security must be expended by the department for the reclamation of the area for which the bond was posted and any remainder returned to the operator.
The board may adopt or amend rules to carry out this subsection, including rules relating to operation or maintenance plans; standards for determining the reclamation period; annual revisions of those plans; limits, terms and conditions on bonds or other security; proof of financial responsibility of a person engaged in excavation activity or the affiliated person who guarantees performance; estimation of reclamation costs; reports on reclamation activities; or the manner of determining when the bond or other security may be discharged. Rules adopted under this subsection are major substantive rules as defined in Title 5, chapter 375, subchapter II-A.
The department may grant a variance from paragraph A, provided that the slopes exhibit substantial vegetation and are stable. The department may not assess a fee for a request for a variance from paragraph A. The department may grant a variance from paragraph E if the applicant demonstrates that the soil is not needed for reclamation purposes. The department may not grant a variance from the other provisions of this subsection.
[2001, c. 466, §9(AMD).]
[2013, c. 405, Pt. D, §17(AMD).]
[2007, c. 297, §7(NEW).]
[2007, c. 616, §5(NEW).]
38 M.R.S. § 490-D