Section 3455 - Determination of public safety-related setbacks

In making findings pursuant to Title 12, section 685-B, subsection 4 or Title 38, section 484, subsection 3 on whether a wind energy development must be constructed with setbacks adequate to protect public safety, the primary siting authority must consider the recommendation of a professional, licensed civil engineer as well as any applicable setback recommended by a manufacturer of the generating facilities. The primary siting authority may require submission of this information as part of the application. [2007, c. 661, Pt. A, §7(NEW).]

35-A M.R.S. § 3455

2007, c. 661, Pt. A, §7 (NEW) .