Me. Stat. tit. 35-A § 3210-D

Current through 131st (2023-2024) Legislature Chapter 684
Section 3210-D - Resource plan

The commission shall adopt by rule a long-term plan for electric resource adequacy for this State to ensure grid reliability and the provision or availability of electricity to consumers at the lowest cost. [2005, c. 677, Pt. C, §1(NEW).]

After final adoption of rules under this section, the commission shall take any necessary action within its authority under this Title to support achievement of the objectives of the plan. [2005, c. 677, Pt. C, §1(NEW).]

Rules adopted under this section are major substantive rules as defined in Title 5, chapter 375, subchapter 2-A. [2005, c. 677, Pt. C, §1(NEW).]

35-A M.R.S. § 3210-D

2005, c. 677, §C1 (NEW) .