Ind. Code § 8-23-9.5-24

Current through P.L. 171-2024
Section 8-23-9.5-24 - Negotiations with another CMGC or PDB; terminating projects

The department may proceed to negotiate a contract under this chapter with another CMGC or PDB, or terminate a project if any of the following occur:

(1) A contract is terminated under section 23 of this chapter.
(2) The department and the selected CMGC or PDB are unable to reach agreement on a contract.
(3) The CMGC or PDB selected under section 18 of this chapter does not provide the required bonds as described in the request for proposals.

IC 8-23-9.5-24

Added by P.L. 60-2023,SEC. 2, eff. 7/1/2023.